The Foundation





The week of August 6th saw the rebar being installed for the foundation walls and the sonotubes being set for the screen porch piers. The following week had Carter's crew coming in to install foundation wall forms and pouring all the concrete walls and piers. By the end of the week, the job was done and all the formwork was gone. Steve and I built the supporting basement frame wall on the 17th before a week off.